Hyde Creek - In-Stream Works Improvement Contract |
|
|
The project involved the reconstruction of retaining walls down the steep embankment along Whatkins Creek. This erosion-prone section was with a new lock block wall retaining system and riprap lining, and also included instream work to enhance environment recovery. |
|
Value |
$295,000 |
|
Year |
2007 |
|
Owner |
City of Coquitlam |
|
Refer to |
Chad Braley, AScT (604-927-3513) |
|
Arch./Eng. |
Earth Tech (Canada) Inc. |
|
Refer to |
Scott Neuman, P.Eng. (604-298-6181) |
|